5 men take 45hours to build a wall.how long will it take 9men working at the same wall?​

Respuesta :

Аноним Аноним
  • 04-03-2022

Answer:

25 hours

Step-by-step explanation:

It takes 5 men 45 hours to build a wall.

So, if no. of men increases by 1.8 [∴ 5 x 1.8 = 9],

then time taken reduces by that same amount.

=> 45 hours / 1.8

=> 45 / (9/5)

=> 45 x 5 / 9

=> 5 x 5

=> 25 hours

Answer Link

Otras preguntas

I NEED HELP NOWW I WILL GIVE THE BRAIN OF KNOWLEDGE!! Multiple Choice 1. Which of the following is true about the electric charges on the objects below?  (1
In the drawer you have 8 black socks and 5 yellow socks , if you pick out a sock what is the probability that the pick out a yellow sock?
Select "Growth" or "Decay" to classify each function.​
Which polynomial function has x intercepts -1,0, and 2 and passes through the point (1,-6)?
ABCD is a square. What is the length of line segment DC? 5 units 7 units 11 units 13 units
Use the model below to calculate 9 ÷ 1 3 please help.9/33/913 1/227
How did the carpet baggers affect southern politics
What aviation first is janice brown credited with
how do you write CRR'S
what is the discriminant of the polynomial below 4x^2-20x +25